Hi, On Tue, Apr 8, 2014 at 2:58 PM, Galen Charlton <gmc@esilibrary.com> wrote:
Wednesday, 30 April: beta release -- by the end of the day, I will clear the Passed QA queue and roll a beta release. A soft string freeze will start upon release of the beta; at this point, translators can be confident that there won't be major string changes.
Monday, 5 May: at the end of the day, a firm string freeze will beginning. I will not call it a hard freeze, as security bugs and release blockers will trump string stability, but translators can expect that there will be no unnecessary changes.
I'm going to combine these two events. In other words, I will release the beta on Monday, and the firm string freeze will start then as well. Regards, Galen -- Galen Charlton Manager of Implementation Equinox Software, Inc. / The Open Source Experts email: gmc@esilibrary.com direct: +1 770-709-5581 cell: +1 404-984-4366 skype: gmcharlt web: http://www.esilibrary.com/ Supporting Koha and Evergreen: http://koha-community.org & http://evergreen-ils.org