[Koha-devel] Timeline for 3.0.1

Chris Cormack chris at bigballofwax.co.nz
Tue Oct 28 08:57:14 CET 2008


On Tue, Oct 28, 2008 at 6:57 AM, Henri-Damien LAURENT
<laurenthdl at alinto.com> wrote:
> Hi,
> As Release Maintainer, I have been given gitosis access to rel3.0
> So I shall be able to catchup with all the bug fixes patches.
>
> What I am aiming at now is issuing a bug fix release on First week of
> December.
> That means, branching 3.0.1 on the 15th November, so that translators
> could have a two weeks time for translations.
>
> Tell me if this sounds reasonable and ok for you (translators).
> You will also need to have the fresher templates. Maybe the Translation
> manager could  have the process update automatically translations and
> allow ppl for multiple version access ?
>
Hi Henri Damien

That sounds like a great idea, Ill make sure the new translation
system is all up and ready for november 15th, with automatic template
generation going.

Chris